If I purchase a 1month pass is that good only from beginning of the month to the end, or if I start Dec 8 is it good til January 8?

Best answer by rvdborgt

It is valid from the day you choose. If you start on 8 December, the the pass is valid up to and including 7 January.

2 replies

Forum|alt.badge.img+10
  • Railmaster
  • Answer
  • March 9, 2023

It is valid from the day you choose. If you start on 8 December, the the pass is valid up to and including 7 January.


JFurf
  • Author
  • Rail rookie
  • March 9, 2023

Thank you for the quick response, that is what I was hoping for but couldn’t find that answer anywhere.